Members are asked to note:
• That Kier, and their Heat Network specialists Hopkins, are
now in contract with Westrock to deliver the District Heat
Network.
• The costs of the contract is within the indicated amount
included within the Revised DHN Budget Report agreed at Council in
March 2020, including a healthy contingency
• The next key milestone for the DHN project will be the
appointment of the O&M contractor
• The new Town Hall building continues to progress in line
with both programme and budget, and the first 91 affordable homes
are due for practical completion in Spring 2021.