11 Appointment of Contractor for Crawley Homes Gas Servicing, Repair and Installation Works

Housing Portfolio

 

(Exempt Paragraph 3)

 

To consider report CH/182 of the Head of Crawley Homes.

 

Minutes:

The Cabinet Member for Housing presented report CH/182 of the Head of Crawley Homes which set out the details of the tender evaluation and to sought approval to appoint a contractor to deliver the gas servicing, repair and installations contract on the termination of the existing contract 31 March 2019. The new contract was for a period of up to 11 years and significant savings would be achieve over the life of the contract.

 

It was noted that there would be a ten day standstill period once all the tenderers involved had been informed of the decision. It was noted this was to allow any challenge on the decision from any of the parties involved. Once this period elapsed the decision would be final and be published accordingly.

 

The Cabinet Member thanked the work of the Working Group for their input of the tender exercise.

 

 

RESOLVED

 

That the Cabinet:

 

a)    approves the appointment of Contractor A on an 11 year Termed Partnering Contract commencing on 1st April 2019 which is subject to an initial 5 year period with renewals at successive two year periods subject to continuous performance monitoring and annual performance review. (Subject to the mandatory standstill period)

 

b)    delegates to the Head of Crawley Homes, in consultation with the Cabinet Member for Housing, to extend the contract for the full term subject to a satisfactory evaluation of the contractor’s service and the future strategic approach on the maintenance services as outlined in 2.1a). (Generic Delegation 9 will be used to enact this recommendation).

 

 

Reasons for the Recommendations

 

The existing Gas Servicing and Repair contract was let for a 10 year period which ends 31 March 2019 and this recommendation seeks to put in place a new contract to ensure service delivery. The contract has been retendered in compliance with the Public Contracts Regulations 2015 and the Council’s Procurement Code.