In finalising the design of the District Heat Network (DHN) and prior to appointing a contractor for the scheme it has become necessary to make budget changes for the DHN. The purpose of this report therefore provide background, to set out the variations scheme and to seek agreement on the way forward that avoids increasing the overall budget for the Town Hall Site Redevelopment project.
Decision type: Key
Reason Key: Expenditure > £500,000;
Decision status: Recommendations Approved
Wards affected: (All Wards);
Notice of proposed decision first published: 28/02/2020
Anticipated restriction: Fully exempt - View reasons
Decision due: 11 Mar 2020 by Cabinet
Decision due: 1 Apr 2020 by Full Council
Lead member: Cabinet Member for Environment, Sustainability and Climate Change, Leader of the Council
Contact: Ian Duke1, Deputy Chief Executive Email: ian.duke@crawley.gov.uk.
Consultation process
N/A