The Town Hall Site Redevelopment has reached
its next key milestone. The Council's Development Managers have
issued a draft Tender Report following discussions and
clarifications. Their recommendation is to issue the contractor
with two Letters of Intent with a view to entering into contract to
build both the New Town Hall and associated works, and the District
Heat Network. This will allow design, procurement and preparatory
works to be undertaken, contract documents to be prepared and final
due diligence checks to take place whilst keeping the projects to
programme ahead of any signing of contracts.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 16/09/2019
Decision due: 2 Sep 2019 by Deputy Chief Executive
Contact: Ian Duke1, Deputy Chief Executive Email: ian.duke@crawley.gov.uk; 01293 438005 Email: ian.duke@crawley.gov.uk.