The Town Hall Site Redevelopment has reached
its next key milestone. The detailed technical design (known as
Stage 4) and related costings in relation to the New Town Hall is
now finalised. Once signed off, this will allow the Council to
proceed to Stage 5 of the project which is to secure the contractor
and undertake construction. The development design (known as Stage
3) for the District Heat Network and related costs has also been
finalised.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 16/09/2019
Decision due: 18 Jun 2019 by Deputy Chief Executive
Contact: Ian Duke1, Deputy Chief Executive Email: ian.duke@crawley.gov.uk; 01293 438005 Email: ian.duke@crawley.gov.uk.