11/09/2019 - New Town Hall Site Redevelopment: Letter of Intent Sign Off ref: 267    Recommendations Approved

The Town Hall Site Redevelopment has reached its next key milestone. The Council's Development Managers have issued a draft Tender Report following discussions and clarifications. Their recommendation is to issue the contractor with two Letters of Intent with a view to entering into contract to build both the New Town Hall and associated works, and the District Heat Network. This will allow design, procurement and preparatory works to be undertaken, contract documents to be prepared and final due diligence checks to take place whilst keeping the projects to programme ahead of any signing of contracts.

Decision Maker: Deputy Chief Executive

Decision published: 16/09/2019

Effective from: 11/09/2019

Decision:

The Deputy Chief Executive, in consultation with the Leader of the Council, the Head of Legal, Democracy and HR has:
• Agreed that the Council's Development Manager will provide the contractor with a Letter of Intent for both the development of the New Town Hall (and associated works) and the District Heat Network, stating our intention to appoint the contractor and allow them to undertake pre-contract works including finalising design, procuring sub-contractors and preparatory works ahead of signing a contract
• This period allows for the contract to be finalised, for final due diligence checks to be made and for communications to be agreed, without adversely impacting upon the programme.
• A further report will be brought prior to any final appointment of a contractor for the New Town Hall and the District Heat Network



Lead officer: Ian Duke1


11/09/2019 - New Town Hall Site Redevelopment: Stage 4 Sign Off ref: 266    Recommendations Approved

The Town Hall Site Redevelopment has reached its next key milestone. The detailed technical design (known as Stage 4) and related costings in relation to the New Town Hall is now finalised. Once signed off, this will allow the Council to proceed to Stage 5 of the project which is to secure the contractor and undertake construction. The development design (known as Stage 3) for the District Heat Network and related costs has also been finalised.

Decision Maker: Deputy Chief Executive

Decision published: 16/09/2019

Effective from: 11/09/2019

Decision:

The Deputy Chief Executive, in consultation with the Leader of the Council, the Head of Legal, Democracy and HR has:
• Signed off on the Stage 4 design process and key changes and the associated costings for the New Town Hall, which allows the Council to move to Stage 5 of the project
• Agreed the approach to procurement for the construction of the New Town Hall and the District Heat Network
• Agreed a further report will be brought prior to the final appointment of a contractor for the New Town Hall and the District Heat Network

Lead officer: Ian Duke1